AI data-centre demand drives search for used turbines

AI · First reported 9 Nov, 06:13 · Updated 06:28

Image: Wikimedia Commons · Ysherazi · CC BY-SA 4.0

With new turbine deliveries stretching years, data-centre developers and other power buyers are seeking used or refurbished gas turbines and repurposed jet engines. These alternatives may ease the supply squeeze only in part, and come with maintenance and operating uncertainties.

  • Orders for gas turbines exceed manufacturing capacity: worldwide orders top 100 GW, against estimated production capacity of 60–70 GW.
  • Buyers are turning to used, refurbished, or jet-engine-based turbines, but analysts say this secondary market is unlikely to offset a meaningful share of delays.
  • Alternative equipment can have unclear maintenance histories or limited remaining life; grid access and permits can also delay projects.
Summary written by Lux AI from 2 articles

Key facts

Worldwide turbine orders
More than 100 GW, compared with estimated global production capacity of 60–70 GW.
Average US turbine delivery time
Six years.
New turbine cost estimate
About $2 million to $2.5 million per MW.
Refurbished turbine cost estimate
About $1.3 million per MW.

Source spectrum

Far left
Left
Lean left
Centre
Lean right
Right
Far right

Left 0 · Centre 2 · Right 0 of 2 rated sources

All coverage

Coverage over time

0106070809
LeftCentreRight

Articles per hour since first reported, by side.

Ownership

  • Unknown 50% (1)
  • Government 50% (1)

Share of the 2 sources by owner type.