Drax says it has agreed with Brookfield and its Radiant platform to develop an AI data centre at the Drax Power Station estate. The proposed project would be built in phases, but requires approvals, a customer and final investment decisions.

  • Drax says it signed an agreement with Brookfield and Radiant to jointly develop an AI data centre at its power station estate in North Yorkshire.
  • The plan targets up to 100 MW from the first quarter of 2028, with another 500 MW targeted between 2028 and 2031; the longer-term aim is to secure more than 1 GW at the site.
  • The initial phase depends on planning, regulatory and network approvals, securing a tenant, and final investment decisions.
Summary written by Lux AI from 2 articles

Key facts

Location
Drax Power Station estate, North Yorkshire
Initial capacity target
Up to 100 MW, targeted from Q1 2028
Further capacity target
500 MW between 2028 and 2031
Estimated investment
Could exceed £20 billion including semiconductors; phase one is initially estimated at £2.5 billion
Outstanding conditions
Approvals, a tenant and final investment decisions remain outstanding

Source spectrum

Far left
Left
Lean left
Centre
Lean right
Right
Far right

Left 0 · Centre 2 · Right 0 of 2 rated sources

Background

All coverage

Coverage over time

0108101214161820
LeftCentreRight

Articles per hour since first reported, by side.

Ownership

  • Corporation 100% (2)

Share of the 2 sources by owner type.